|
- A Guide to the Project Management Body of Knowledge,
Chapter 12 (1996 & 2000 edition)
- PMBOK Q&A, PMI, Procurement |
| Principles of Project Management, pgs. 213-280, John Adams |
| The New Project Management, Chapter 10, Frame, J. Davidson, 1994 |
| Project Management, A Systems Approach to Planning, Scheduling & Controlling., Chapter 24, Kerzner |
| PMP Challenge!, ESI International, Procurement Management Section |
| Estimated Cost | $1,000K |
|---|---|
| Percentage | 10% ($100K) |
| Estimated Total Price |
$1,100K
(Estimated Cost + 10% * Estimated Cost) |
| If cost increases to $1,100K the total price would be $1,100K plus 10% of the actual costs = $1,210K. | |
| Estimated Cost | $1,000K |
|---|---|
| Percentage | 10% ($100K) |
| Estimated Total Price |
$1,100K
(Estimated Cost + 10% * Estimated Cost) |
| If cost increases to $1,100K the total price would be $1,100K plus 10% of the original estimated costs = $1,200K. | |
| Estimated Cost | $1,000K |
|---|---|
| Predetermined Fee | $100K |
| Sharing Formula |
85/15
(buyer absorbs 85% of the uncertainty and the seller absorbs 15% of the risk) |
| Actual Cost | $800K |
| Savings | $200K |
| Seller Gets |
$800K + $100K + $30K = $930K
(Actual cost + Fee + (15% * Savings)) |
| Buyer Saves | $170K |
| Target Cost | $1,000K |
|---|---|
| Target Profit | $100K (Seller's Fee) |
| Target Price | $1,100K |
| Ceiling Price | $1,200K (The maximum pay-out to the seller) |
| Share Ratio | 70/30 |
| EXAMPLE A | |
| Actual Cost | $800K |
| Savings |
$200K
(Target cost - Actual cost) |
| Seller Gets |
$800K + $100K + 60K = $960K
(Actual cost + fee + 30%*savings) |
| Buyer Saves | $140K |
| EXAMPLE B | |
| Actual Cost | $1,300K |
| Seller Gets |
$1,200K
(no profit and a $100K loss on costs) |
| Buyer Loses |
$100K
(the pay-out is $100K over Target price = Ceiling Price) |
| Price | $1,000K |
|---|---|
| EXAMPLE A | |
| Actual cost | $700K |
| Seller's Profit |
$300K
(Price - Actual Cost) |
| EXAMPLE B | |
| Final cost | $1,100K |
| Seller's Loss | $100K on contract |